Gas sweetening site with amen

Technical specifications of gas sweetening site with amen

Piping:

Fit-up: 32000” dia inch

Materials:CS/SS

SCH:S10S-S40-S80-S160

Welding:

Fit-up: 32000” dia inch

Materials:CS/SS/LTCS

SCH:S10S-S40-S80-S160

Install Spool:

SPOOL: 1265/PCS

Support piping:

SUPPORT: 763 PCS

TOTALL WIGHT: 57000KG

Materials: CS

Test operation:

HYDROTEST: 22000” DIA INCH

RANGE (BAR): 5.25bar ~ 85bar

STATIC TEST: 10000” DIA INC

TEST MEDIUM: FRESH WATER

Project duration:

DURATION: 18 MONTH

Location of the project:

Iraq-Erbil-Persimmon website

Employers:

Company: KAR GROUP

Company: LAFAWEBAHEZ